                                                           Project Manager: Alper ÖZKAN



                                                                                                   st
                   The tender related to the Eyiste Viaduct has been conducted by the KGM on November 21 , 2016 and the contract has been
                                                                                                           th
                   awarded to Nurol Construction and Trading Co. Inc. Main contract has been signed on December 15 , 2016 and the contract
                                                                          th
                   duration of 1.100 days has been commenced on December 29 , 2016 triggered by the issuance of construction site delivery
                   letter by the KGM.
                   Within the scope of the project, a bridge with a length of 1.372 meters and a total width of 25 meters will be constructed.
                   The superstructure will be constructed on 2 abutments and 8 piers with varying heights between 31 meters and 155 meters.
                   Construction is ongoing in accordance with the work schedule.

                   Foundation excavation and piling works are planned to be completed shortly, and foundation and elevations works are on-