NATIONAL
Eyiste Viaduct
Project
Project Manager: Alper ÖZKAN
st
The tender related to the Eyiste Viaduct has been conducted by the KGM on November 21 , 2016 and the contract has been
th
awarded to Nurol Construction and Trading Co. Inc. Main contract has been signed on December 15 , 2016 and the contract
th
duration of 1.100 days has been commenced on December 29 , 2016 triggered by the issuance of construction site delivery
letter by the KGM.
Within the scope of the project, a bridge with a length of 1.372 meters and a total width of 25 meters will be constructed.
The superstructure will be constructed on 2 abutments and 8 piers with varying heights between 31 meters and 155 meters.
Construction is ongoing in accordance with the work schedule.
Foundation excavation and piling works are planned to be completed shortly, and foundation and elevations works are on-
going.