ACTUAL TOTAL COST
$51.083.627
EARTH WORKS
%48
MINOR
STRUCTURES
SECONDARY %26
WORKS %6
PAVEMENT
WORKS
TOLL
COLLECTION GEOTECHNICAL LARGE
%1 LANDSCAPE WORKS %7 STRUCTURES %8
%4
AS of March 31, 2016 (Un t pr ce 2010)
Actual total cost of the project is 51.083.627 USD as per 2010 unit prices and distribution of the total amount according to work items are
shown at the graphic 1.
Within the scope of the project 6 million m³ excavation and fill, over 90.000 m³ concrete and over 8.000 tonnes of structural reinforcement
works were completed. Total works are shown on Table 1. Finishing works were completed on main road, service and toll collections areas
besides landscaping. Junction lightings, guardrail, ROW fence, traªc signs and road markings were constructed by NOMAYG(Employer).
Gebze - Orhangazi - İzmir
Final account works for this section is about to be completed.