NATIONAL
Silifke-Mut
Motorway Project
th
The tender related to the Silifke-Mut Motorway Km: 0+000-16+700 has been conducted by the KGM on August 24 , 2017
and the contract has been awarded to Nurol Construction and Trading Co. Inc. Main contract has been signed on October
th
th
4 , 2017 and the contract duration of 1.150 days has been commenced on October 19 , 2017 triggered by the issuance of
construction site delivery letter by the KGM.
Within the scope of the project, II. Kılıç Arslan Bridge, balanced cantilever bridge with a cable stay system having a length
of 410 meters, 3 motorway tunnels with a total length of approximately 7 kilometers in addition to other works including
earthworks, engineering structures and pavement works on the project route will be realized.
Mobilization works and selection of subcontractors and vendors are ongoing in accordance with the work schedule.