Yusufeli Group of
Viaducts
Project
Project Manager: Serkan ÇELİKÖRS
The tender related to the Yusufeli Group of Viaducts has been
st
conducted by the KGM on June 5 , 2017 and the contract has
been awarded to Nurol-Gülsan Joint Venture. Main contract
st
has been signed on June 21 , 2017 and the contract duration
of 900 days has been commenced on July 7 , 2017 triggered
th
by the issuance of construction site delivery letter by the
KGM.
Within the scope of the project, Tekkale (Hazuket) Viaduct
with a length of 644 meters, Yusufeli Viaduct with a length
of 695 meters, Yusufeli Dam Viaduct with a length of 340
meters and Silenkar Viaduct with a length of 530 meters will
be constructed.
Mobilization works and selection of subcontractors and
vendors are ongoing in accordance with the work schedule.