Within  the  scope  of  the  project  with  a  total  contract  values  of
                                                                        $454.543.319 as per 2010 unit prices, earth works, minor and large
                                                                        structures (6 viaducts with a total length of 4.436 m.), pavement
                                                                        works (wetmix and hotmix), geotechnical works, landscaping, toll
                                                                        collection and secondary works (utility works, service and parking
                                                                        areas, maintenance centers) will be constructed. Traffic signs,
                                                                        road marking, guardrail and Row fence constructions are excluded
                                                                        and will be contracted out by NÖMAYG separately. Coordination
                                                                        and supervision of the construction works of those items will be
                                                                        on responsibility of NUROL.
                                                                        By the end of 2016 project goals has been mostly accomplished.
                                                                        Works on minor and large structures, earthworks, viaducts,
                                                                        drainage, pavements and prestressed beams are proceeding on
                                                                        all sections as of February 2017. 40% progress were realized on
                                                                        construction works since the begining of the project (Graphic 4).
                                                                        Quantitive amounts in project and realizations as of end of May
                                                                        2017 are shown at Table 4.
                                                                        According to planning of 2017, 6,9 million m³ excavation on main
                                                                        road, 5,5 milion m³ borrow pit excavation, 600.000 m³ topsoil
                                                                        excavation,  10,7 milion m³ fill, 198.000  m³ reinforced  concrete,
                                                                        41.000 m³ surface drainage concrete, 1.690 number of prestressed
                                                                        beams, 6.300 m. bored pile, 1.600.000 tonnes wetmix pavement,
                                                                        700.000 tonnes hotmix pavement and utility relocations are
 Gebze - Orhangazi  - İzmir                                             End date is 31.12.2018 according to contract.
                                                                        planned to be completed.