Page 17 - World Of Nurol Magazine 28
P. 17
Within the scope of the project with a total contract values of
$454.543.319 as per 2010 unit prices, earth works, minor and large
structures (6 viaducts with a total length of 4.436 m.), pavement
works (wetmix and hotmix), geotechnical works, landscaping, toll
collection and secondary works (utility works, service and parking
areas, maintenance centers) will be constructed. Traffic signs,
road marking, guardrail and Row fence constructions are excluded
and will be contracted out by NÖMAYG separately. Coordination
and supervision of the construction works of those items will be
on responsibility of NUROL.
By the end of 2016 project goals has been mostly accomplished.
Works on minor and large structures, earthworks, viaducts,
drainage, pavements and prestressed beams are proceeding on
all sections as of February 2017. 40% progress were realized on
construction works since the begining of the project (Graphic 4).
Quantitive amounts in project and realizations as of end of May
2017 are shown at Table 4.
According to planning of 2017, 6,9 million m³ excavation on main
road, 5,5 milion m³ borrow pit excavation, 600.000 m³ topsoil
excavation, 10,7 milion m³ fill, 198.000 m³ reinforced concrete,
41.000 m³ surface drainage concrete, 1.690 number of prestressed
beams, 6.300 m. bored pile, 1.600.000 tonnes wetmix pavement,
700.000 tonnes hotmix pavement and utility relocations are
Gebze - Orhangazi - İzmir End date is 31.12.2018 according to contract.
planned to be completed.
Motorway Construction
17
28 SAYI DERGI NUROL ING.indd 17 20.07.2017 22:26:08