NATIONAL





































                    Gebze - Orhangazi  - İzmir






                         Motorway Construction







                                                    Gebze  - Orhangazi Section
              Project Manager: Yavuz YONTEM

                                                                                              The construction works within the scope of
                                                                                              contract that NUROL signed with NÖMAYG
                                                                                              (Employer)  for  the  construction  works  of
                                                                                              section approximately 9 km length that takes
                                                                                              place between Gebze - Orhangazi (Ch: 34+350-
                                                                                              43+296) of “Gebze - Orhangazi - İzmir Motorway
                                                                                              (Including Izmit bay suspension bridge and
                                                                                              access roads )” (Figure 1), which is constructed
                                                                                              with Build-Operate-Transfer model under the
                                                                                              obligation of Otoyol A.Ş. (Company In Charge)
                                                                                              has been completed by the end of March 2016.
                                                                                              This section of motorway was opened to the
                                                                                              traffic on April 2016. Responsibility area of
                                                                                              NUROL takes place between Samanlı Tunnel
                                                                                              exit and Orhangazi settlement. (Figure 2).
                                                                                              Earth works, structures, geotechnical works,
                                                                                              landscape, toll collection and secondary works
                                                                                              (utility relocations, service and park areas) are
                                                                                              under the responsibility of NUROL, pavement
                                                                                              works are excluded. In addition to service area
                                                                                              on Ch:37+500, K4 Junction and toll collection
                Şekil 1                                                                       area were constructed on Ch: 40+000 of the
                                                                                              Motorway.