Page 22 - World Of Nurol Magazine 28
P. 22
NATIONAL
Gebze - Orhangazi – İzmir
Motorway
The tender for the Gebze-Orhangazi-İzmir Motorway Project Current Structure Summary of Ongoing Design Studies
(including İzmit Bay Crossing and Connection Roads) was
made on 9 April 2009 and the 22 years 4 months construction MAIN CONSTRUCTION ITEMS TOTAL NOS
and operation offer was determined as the best and final. SUSPENSION BRIDGE 1
TUNNEL 3
Implementation Contract was signed on 27 September
2010 between General Directorate of Highways and OTOYOL VIADUCTS 38
YATIRIM ve İŞLETME A.Ş.. Following the signing of the Reinforcement 36
contract OTOYOL A.Ş. has started to construction with Steel 1
the use of equity in line with Implementation Contract. Composite 1
As of 5 June 2015, the entire financing requirement of the
Project has been completed. Construction works continue BRIDGES 175
to accelerate. Overpass 88
Underpass 47
A total of approximately 6271 personnel are employed in the
Gebze-Orhangazi-İzmir Motorway Project in the direction of Hydraulic 39
January 2017 month data. Composite 1
BOX CULVERTS 987
A total of 433 km motorway is being constructed as 384 km Box Culuert (Underpass) 284
motorway and 49 km connection roads.
Box Culvert(Hydraulic) 703
Project Characteristic Information: INTERSECTION 24
MOTORWAY SERVICE AREA 18
• Motorway Main Body: 384 km
• Existing Bursa Ring Road (Open to Traffic): 21 km MOTORWAY OPERATION - MAINTENANCE 4
• Total Motorway Main Body: 405 km FACILITY
• Connection Roads: 49 km TUNNEL OPERATION FACILITY 2
• Intersection Roads: 140 Km
• Side Roads: 26 Km
*3 nos intersections including Existing Bursa Ring Road.