                              Eyiste Viaduct







                                                   Project







                                                            Project Manager: Alper OZKAN
                                                                                                   st
                   The tender related to the Eyiste Viaduct has been conducted by the KGM on November 21 , 2016 and the contract has been
                                                                                                           th
                   awarded to Nurol Construction and Trading Co. Inc. Main contract has been signed on December 15 , 2016 and the contract
                                                                          th
                   duration of 1.100 days has been commenced on December 29 , 2016 triggered by the issuance of construction site delivery
                   letter by the KGM.
                   Within the scope of the project, a bridge with a length of 1.372 meters and a total width of 25 meters will be constructed.
                   The superstructure will be constructed on 2 abutments and 8 piers with varying heights between 31 meters and 155 meters.
                   Mobilization works and selection of subcontractors and vendors are in progress in accordance with the work schedule.
                   Construction is planned to be commenced within April 2017.














                   Nurettin AKDENİZ, Tayfur İKİZÜNAL(Offical of
                      General Directorate of State Highways)








             18



         28 SAYI DERGI NUROL ING.indd   18                                                                                  20.07.2017   22:26:09
   13   14   15   16   17   18   19   20   21   22   23