ALGERIA




















            Regional Manager: Nurettin DEMİR






































                  Traffic jam and low standards of the current public road  the region of Djebahıa will be the longest viaduct of Algeria.
                  (RN25) between the cities of Tizi Ouzou and Bouıra causes  The spans on the balanced cantilever viaducts are almost 150
                  difficulties for transportation. A 48 km. highway construction  m and on the highway there are also 2 tunnels  1,57 km length
                  which is alternative to the RN25 public road has been given  in total. The tunnel section is nearly 180 m as planed 2*3.
                                                                                                                   2
                  to the partnership of  Ozgun-Nurol-Engoa (GROUPEMENT  The project is important as the first highway to be constructed
                  O.N.E.) by  the Algerian Directorate  of Highways (Agence  by Nurol and Ozgun companies in Algeria and 19% of the
                  National Des Autoroutes) with a 538 million euro valued  project has been completed.
                  agreement signed on 12.02.2014.

                  The region is under the effect of Mediterranean rainy climate  MAIN CONSTRUCTION QUANTITIES WITHIN THE PROJECT
                  conditions and geographic features are mostly steep. Project
                  and excavation works started partially in May 2014 and it  24.9 million m  route excavations
                                                                                         3
                  gained acceleration with the start of viaduct and tunnel  7,5 million m  route fill
                                                                                        3
                  constructions in May 2015.                                1,3 million m  concrete
                                                                                        3
                                                                            130.000 tonnes reinforcing bar
                  The 48 km. long project, an important linking road on the  800.000 tonnes cement
                  East-West highway, has been planned as 2*3.  There  are  9  3,5 million tonnes aggregate
                  crossroads, 15 underpasses and overpasses on the route. In  122.000 meter bored excavations
                  addition, 21 viaducts (10,5 km) are being constructed; 10 of  2.200 precast beams
                  them (3 km) planned with precast beam and 11 of them (7,  10.000 tonnes steel rope
                  5 km) planned as balanced cantilever viaduct. The Djebahıa  45.000 tonnes bituminous material
                  viaduct which is totally 1773 m long -567 m. planned with  970.000 tonnes hot mixture
                  precast beam and 1206 m planned as balanced cantilever- in  1,5 million tonnes base