DOUERA                                      The Douera Dam, located near Douera district and 27 km
                                                                     southern west of Algiers, the capital city, is the  first project
                                                                     having been realized in Algeria by NUROL. The Douera Dam
                                                                     shall provide potable water for the Alger city as well as irrigation
                                                                     water to the farm lands (17.200 Ha) in the Mitidja plain.  The
                                                                     Dam was totally completed including the works of the 2 years
                                                                     warranty period that the final acceptance was performed on 5
                                                  DAM                The inauguration of the Dam was performed on 4 July 2016 by
                                                                     October 2016.

                                                                     his excellency Abdulmalek SELLAL, Prime Minister of Algeria,
                                                                     and the reservoir impounding had been initiated since then.

























             The Souk Tleta Dam, the second project of NUROL in Algeria,
             embankment. The project consists of two 9 m diameter diversion  SOUK
                                 3
             has a 100 million m  water-retention capacity, which will be
             used for potable water supply to Boumerdes and Algiers cities of
             the Country.  The Dam is a zoned earth fill embankment with a
                                         3
             total quantity of 3.000.000 m  earth-moving including the side
             the expropriation problems in the lake area and because of the TLETA
             tunnels of each 375 m length,  a scheme of injection galleries
             totally 750 m length, 105.000 m³ concrete and 50.000 m drilling
             for the grout curtain.
             The project has remained suspended for a long time owing to
             incomplete relocation of the RN25 highway passing through
             the construction site of the dam. The project works have been
             performed at present at an accelerated pace with the aim at DAM
             resumed since 17 July 2016 upon resolution of the  expropriation
             problems and the re-settlement issues. Construction works are
             realization of the river diversion within the first half of the year
             2017.  Besides,  works  are  performed  for  completion  of  the  side   Project Manager: Kamil İlhami GÜMÜŞDAĞ
                                      3
             embankment of 200.000 m  volume within the year 2016.