Was the starting of the project postponed  Phase 2A represents Gemlik- Bursa section  Were there unforeseen circumstances in
                due to the time delay in the supply of  and Phase 2B represents Bursa-İzmir  the implementation process of the project?
                the  planned  loan?  How  was  this  problem  section.                       At what points there were processes that
                overcome?                             Phase 1 has been completed and opened for  did not conform to the work schedule and
                                                      operation and was financed with our first  why?
                Before the start of the project in 2013, the  loan in 2013. Phase 2A was financed with the
                shareholders of our company provide equity  loan in 2014 and Phase 2B was financed with  We encountered unexpected situations in
                in  the amount  of  600 million  US Dollars  the loan in 2015.               the process of carrying out the expropriations
                starting from 2009 and thus prevented any  The loan package in 2015 also re-financed  from time to time but I can tell you that
                delay being encountered in the project.   the original loans of Phase 2A and Phase 2B.  both the administration and the related
                                                                                             government  bodies  made   significant
                How was the division of works accomplished  Are all the motorways on the route of the  contributions for solutions and used all their
                among the partners? Did it not carry a risk  project being newly constructed or are there  means to pave the way for us for this project.
                to subcontract some of the works to firms  existing state highways that will be used.
                outside the group (for example, Samanlı  Can we have some information on this  An important component of the project
                Tunnel, the longest tunnel in Turkey)?  subject?                             is İzmit Bay Crossing Bridge, which will
                                                                                             be named “Osmangazi Bridge”, has been
                After the Motorway Works are divided into  When the project is completed, it will have a  opened on 30 June 2016 and began to provide
                equal sections on the basis of cost, division  Main Body Length of 405 Km. Of this length,  service. Can we have some information?
                among the partners was made by drawing  384 km shall be constructed by our Assigned
                lots. In Phase I, the work items that require  Company (Otoyol Investment and Operation  Subcontractor: IHI-ITOCHU Consortium
                special expertise such as Suspension  Inc.) within the scope of Build-Operate-  Contract Price: 1,114,489,552 USD
                Bridge, Samanlı Tunnel, Southern Approach  Transfer Model, 21 km is the existing Bursa  Contract Period of the Work: 37 Months
                Viaduct were given to firms that are expert  Peripheral Way built by KGM and opened  Completion Time: 42 Months
                in their works and that meet the eligibility  to traffic. In addition  to the 384 km Main
                criteria through tenders. Regarding the  Body Motorway construction, our Assigned  The bridge was constructed at a very critical
                construction works responsibilities, the  Company will perform the construction of  location regarding earthquake, very close
                road between Gebze-İzmir was divided  connection roads, junction arms, existing  to the North Anatolia Fault Line; with
                into 7 different sections and motorway  state highway arrangements and side roads  what kinds of studies and solutions were
                construction works were subcontracted  I mentioned above and open them to traffic.  the disadvantages  of this  situation  was
                by NÖMAYG A.O. to firms according to the                                     overcome?
                breakdown given in Table 1 and Table 2  What are the important structures that we
                below.                                can call milestones of the project?    The Suspension  Bridge  is located  quite
                                                                                             close  to  North  Anatolia  Fault,  which  is
                What is meant exactly by terms Phase 1,  Important Structures:               one of the most active seismic regions
                Phase 2A – Phase 2B that we hear frequently  For Phase I: Suspension  Bridge, Southern  of  the world.  For this reason, NÖMAYG
                when discussing financial matters?    Approach   Viaduct,  Orhangazi  Tunnel  selected American  FUGRO Company for
                                                      (Samanlı) and Viaducts.                geotechnical,  geological and seismological
                They refer to the motorway sections in the  For Phase II A: Selçukgazi Tunnel and  assessment,  which  is  one  of  the  most
                loan agreements. Phase 1 represents Gebze-  Viaducts                         trustworthy companies in the world on the
                Gemlik section including Osmangazi Bridge,  For Phase II B: Belkahve Tunnel and Viaducts  subject. FUGRO Company completed all