NATIONAL





































                 Gebze  -  Orhangazi  -  İzmir






                            Highway Construction







                                                     Gebze – Orhangazi Section
              Project Manager: Yavuz YÖNTEM

                                                                                              The construction works within the scope of
                                                                                              contract that NUROL signed with NÖMAYG
                                                                                              (Employer) for the section approximately 9
                                                                                              km length that takes place between Gebze -
                                                                                              Orhangazi (Ch: 34+350-43+296) of  “Gebze -
                                                                                              Orhangazi - İzmir Motorway (Including Izmit
                                                                                              bay  suspension  bridge  and  access roads  )”
                                                                                              (Figure 1), which is constructed with Build-
                                                                                              Operate-Transfer model under the obligation
                                                                                              of Otoyol A.Ş. (Company In Charge) has been
                                                                                              completed by the end of March 2016. This
                                                                                              section of motorway was opened to the
                                                                                              traffic on April 2016. Responsibility area of
                                                                                              NUROL takes place between Samanlı Tunnel
                                                                                              exit and Orhangazi (Figure 2). Earth works,
                                                                                              structures, geotechnical works, landscape,
                                                                                              toll collection and secondary works (utility
                                                                                              relocations, service and park areas) are under
                                                                                              the responsibility of NUROL, pavement works
                                                                                              are excluded. In addition to service area on
                                                                                              Ch:37+500, K4 Junction and toll collection
                Figure 1                                                                      area were constructed on Ch: 40+000 of the
                                                                                              Motorway.