PROJECT CONTRACT VALUE Within the scope of the project, earth works, minor and
large structures (6 viaducts with a total length of 4.436 m.),
$ 454.543.319 pavement works (wetmix and hotmix), geotechnical works,
landscaping, toll collection and secondary works (utility
works, service and parking areas, maintenance centers)
will be constructed. Traffic signs, road marking, guardrail
and Row fence constructions are excluded and will be
contracted out by NÖMAYG separately. Coordination and
supervision of the construction works of those items will be
$ 101.231.374 on responsibility of NUROL.
24%
By the end of September 2016 works on minor and large
$ 344.311.945 structures, cut and fill, viaducts drainage, pavements and
76% prestressed beams are proceeding on all sections. 24%
progress were realized on construction works since the
begining of the project (Graphic 4). Quantitive amounts in
project and realizations as of end of September 2016 are
shown at Table 4.
As of September, 2016
Completed Remaining According to planning of 2016, 11,2 million m³ excavation on
main road, 1,6 milion m³ borrow pit excavation, 1,1 milion m³
Graphic 2 topsoil excavation, 11,4 milion m³ fill, 368.000 m³ reinforced
concrete, 22.000 m³ surface drainage concrete, 450 number
of prestressed beams, 4.000 m. bored pile, 300.000 tonnes
wetmix pavement, 150.000 tonnes hotmix pavement and
utility relocations are planned to be completed. Contract
Gebze - Orhangazi - İzmir end date is 31.12.2018.
Highway Construction