Page 23 - World Of Nurol Magazine-27
P. 23

PROJECT CONTRACT VALUE                           Within  the  scope  of  the  project,  earth  works,  minor  and
                                                                         large structures (6 viaducts with a total length of 4.436 m.),
                                 $ 454.543.319                           pavement works (wetmix and hotmix), geotechnical works,
                                                                         landscaping, toll collection and secondary works (utility
                                                                         works, service and parking areas, maintenance centers)
                                                                         will be constructed. Traffic signs, road marking, guardrail
                                                                         and Row fence constructions are excluded and will be
                                                                         contracted  out  by  NÖMAYG  separately.  Coordination  and
                                                                         supervision of the construction works of those items will be
                          $ 101.231.374                                  on responsibility of NUROL.
                              24%
                                                                         By the end of September 2016 works on minor and large
                                         $ 344.311.945                   structures, cut and fill, viaducts drainage, pavements and
                                              76%                        prestressed beams are proceeding on all sections. 24%
                                                                         progress were realized on construction works since the
                                                                         begining of the project (Graphic 4). Quantitive amounts in
                                                                         project and realizations as of end of September 2016 are
                                                                         shown at Table 4.
                                 As of September, 2016
                               Completed     Remaining                   According to planning of 2016, 11,2 million m³ excavation on
                                                                         main road, 1,6 milion m³ borrow pit excavation, 1,1 milion m³
                    Graphic 2                                            topsoil excavation, 11,4 milion m³ fill, 368.000 m³ reinforced
                                                                         concrete, 22.000 m³ surface drainage concrete, 450 number
                                                                         of prestressed beams, 4.000 m. bored pile, 300.000 tonnes
                                                                         wetmix pavement, 150.000 tonnes hotmix pavement and
                                                                         utility relocations  are planned  to  be completed.  Contract
 Gebze  -  Orhangazi  -  İzmir                                           end date is 31.12.2018.





 Highway Construction














































                                                                                                                                23