Launching and Heavy Lifting




                                                     Operations






                 Combination of Incremental Launching and Heavy Lifting  In the first sequence of heavy lifting operation 2.350
                 Operations provide uniqueness to the South Approach  tons,118  meters  length  deck  is  lifted  and  erected  to  60
                 Viaduct Construction.                                  meters height. At the second phase 2.600 tons, 128 meters
                                                                        length deck is lifted and erected to the 57 meters height.
                 22.500 tons weight, 1.123 meters length deck launched to  Both are natioal record.
                 it’s project location in 15 months as a world record.












 Steel Pier and Deck




 Manufacturing            Waterproofing and Asphalt



                                                             Works



                  When steel manufacturing works have been finished, surfaces of the viaduct located under the asphalt layer and
                  walkways isolated for waterproofing with membrane. Finally, 28 mm mastic and 32 mm stone mastic asphalt laid on
                  traffic flow zone.