Actual total cost of the project is 49.484.998 USD as per 2010 unit prices and distribution of the total amount according to work items are
shown at the graphic 2.
Within the scope of the project 6 million m³ excavation and fill, over 90.000 m³ concrete and over 8.000 tonnes of structural reinforcement
works were completed. Total works are shown on Table 1 in detail and quantitive realizations as of end of March 2016 are shown on Table 2.
Finishing works were completed on main road, service and toll collection areas besides landscaping. Junction lightings, guardrail, Row fence,
Gebze - Orhangazi - İzmir
traffic signs and road markings were constructed by NOMAYG (Employer).
Highway Construction
Graphic 1
Figure 2