Page 55 - World Of Nurol Magazine-26
P. 55

ACTUAL TOTAL COST
                                                                                           $49.147.687


                                                                                      EARTH WORKS  %49



                                                                                                            MINOR
                                                                                                          STRUCTURES
                                                                    SECONDARY                                %27
                                                                    WORKS %6

                                                                  PAVEMENT WORKS


                                                                  TOLL COLLECTION
                                                                      %1              GEOTECHNICAL   LARGE STRUCTURES
                                                                             LANDSCAPE
                                                                                %3     WORKS  %6       %8
                                                                                     AS of December 31, 2015 (Unit price 2010)
                                                                  Graphic 1
           Figure 2


        Actual total cost of the project is 49.147.687 USD per 2010 unit
        prices and distribution of the total amount according to work
        items are shown at the graphic 2.

            PROJECT (KM: 34+350 – 43+296)










 Gebze  -  Orhangazi  -  İzmir





 Highway  Construction



                                                                  Table 2




          Table 1
          Works under NUROL’s contract commenced on 22.11.2011 with
          the “Notice to Proceed”. Mobilization works are completed
          on February 2012 and as end of December 2015, physical and
          financial realization reached 100% level.

          Within the project over 6 million m³ excavation and fill, over
          90.000 m³  concrete and over 8.000 tonnes of structural
          reinforcement works were completed.

          Total works are shown on Table 1 in detail and quantitive
          realizations as of end of December 2015 are shown on Table
          2. Finishing works are under progress on main road service
          and toll collections areas besides landscaping. Opening the
          road to traffic is targeted by the end of January 2016. Junction
          lightings, guardrail, Row fence, traffic signs and road
          markings to be completed by NOMAYG(Employer) before the
          road is opened to the traffic.