Page 53 - World Of Nurol Magazine-26
P. 53
There are 7 viaduct with total 3.105 m
length, 6 tunnel with 18.759 m (single
tube) length, total 6 crossway of which
3 of them are bridged take place at Ordu
Beltway which will be constructed as 26
m platform width 2x2 m divided road.
In spite of very bad ground conditions
since the project started, 11.816 m
(single tube) tunnel excavation is
completed, 8.910 m tunnel cincture
concrete paving is made. Excavation
works of 3.311 m (single tube) Boztepe
Tunnel and 2.019 m (single tube) Öceli
Tunnel are finished. It is reached to
final stage at the construction of 785
m length Civil Viaduct. Apart from all of
Contract of Ordu Beltway Project, of which the construction is undertaken these, construction of craft structures,
by Nurol-Yüksel-Özka-YDA Partnership, signed on February 7, 2012 and earth works and other manufacturings
the construction is started on March 20, 2012. Ordu Beltway disconnects continue.
from Akçaova River, goes under Boztepe with tunnel, passes Civil Brook,
Melet River and Turnasuyu with viaduct and connected to coast road
ahead of Turnasuyu Village. With the change of itinerary total project
length reach to 21.4 km from 19.1 km.
53