Within the scope of the Project, earth works, minor and large   By end of December 2015, minor structures and earth works on
        structures (6 viaducts with a total length 4.436 m.), pavement   section Ch: 224+300 – 267+000 and works on Ertuğrul, Köyyeri
        works (wetmix and hotmix), geotechnical works, landscaping,   and Savaştepe viaducts commenced and proceeding. By the end
        toll collection and secondary works (utility works, servicing and   of 2015, 9% progress is made on construction works (Graphic 4).
        parking areas, maintenance centers) will be constructed. Traffic   Mobilization of other site offices are under progress, meanwhile
        signs, road marking, guardrail and Row fence constructions are   construction works at Kırkağaç – Akhisar section commenced in
        excluded  and will be contracted out by NÖMAYG separately.  December 2015.

                                                                  Quantitive amounts in Project and realizations as of end of
                                                                  December 2015 are shown at Table 4. According to planning of
                            PROJECT CONTRACT VALUE
                                                                  2016, 11 million m3 excavation on main road, 1,7 milion m³ borrow
                                                                  pit  excavation, 1,2 milion  m³ topsoil excavation, 12.7  milion
                                                                  m³ fill, 334.000 m³ reinforced concrete, 22.000 m³ concrete
                                                                  trenches, 450 number of prestressed beams, 4.000 m. bored
                                    $414.332.715
               $40.210.604             %91                        pile, 300.000 tonnes wetmix pavement, 150.000 tonnes hotmix
                   %9                                             pavement and utility relocations are planned to be completed.
                                                                  Contract end date is 31.12.2018.






                                As of June 30, 2015
                                 As of December, 2015
                 Actualized Manufacturing Amount   Balance Manufacturing Amount
                                          Remaining
                 Completed
             Graphic 4



             T STRUCTURES LIST BETWEEN KM: 224+300 AND 317+284
             TYPE                             PIECE

          Box Culvert                           223
          Underpass                             75
          U type RC Canal                       10
          Retaining Wall                         6
          Underpass Bridge                      15
          Overpass Bridge                       22
          Viaduct                                6
          Prestressed Beam                     2944
          Bored Pile (m)                      19.642 m
             Table 3

                                 TOTAL
                                QUANTITY
                            CH                 (As of December 31, 2015)

                                                 5.448.979 m 3
                                                 2.789.807 m 3

          Concrete                               135.563 m 3

                                     tonnes
                                     tonnes
             Table 4


        Within the scope of the Project, mobilization works on Ertuğrul
        worksite at Ch:238+000 are completed at the end of March
        2015 and construction works on the site commenced on early
        April 2015 with employer’s instruction letter dated 06.03.2015.