Within the scope of the Project, earth works, minor and large By end of December 2015, minor structures and earth works on
structures (6 viaducts with a total length 4.436 m.), pavement section Ch: 224+300 – 267+000 and works on Ertuğrul, Köyyeri
works (wetmix and hotmix), geotechnical works, landscaping, and Savaştepe viaducts commenced and proceeding. By the end
toll collection and secondary works (utility works, servicing and of 2015, 9% progress is made on construction works (Graphic 4).
parking areas, maintenance centers) will be constructed. Traffic Mobilization of other site offices are under progress, meanwhile
signs, road marking, guardrail and Row fence constructions are construction works at Kırkağaç – Akhisar section commenced in
excluded and will be contracted out by NÖMAYG separately. December 2015.
Quantitive amounts in Project and realizations as of end of
December 2015 are shown at Table 4. According to planning of
PROJECT CONTRACT VALUE
2016, 11 million m3 excavation on main road, 1,7 milion m³ borrow
pit excavation, 1,2 milion m³ topsoil excavation, 12.7 milion
m³ fill, 334.000 m³ reinforced concrete, 22.000 m³ concrete
trenches, 450 number of prestressed beams, 4.000 m. bored
$414.332.715
$40.210.604 %91 pile, 300.000 tonnes wetmix pavement, 150.000 tonnes hotmix
%9 pavement and utility relocations are planned to be completed.
Contract end date is 31.12.2018.
As of June 30, 2015
As of December, 2015
Actualized Manufacturing Amount Balance Manufacturing Amount
Remaining
Completed
Graphic 4
T STRUCTURES LIST BETWEEN KM: 224+300 AND 317+284
TYPE PIECE
Box Culvert 223
Underpass 75
U type RC Canal 10
Retaining Wall 6
Underpass Bridge 15
Overpass Bridge 22
Viaduct 6
Prestressed Beam 2944
Bored Pile (m) 19.642 m
Table 3
TOTAL
QUANTITY
CH (As of December 31, 2015)
5.448.979 m 3
2.789.807 m 3
Concrete 135.563 m 3
tonnes
tonnes
Table 4
Within the scope of the Project, mobilization works on Ertuğrul
worksite at Ch:238+000 are completed at the end of March
2015 and construction works on the site commenced on early
April 2015 with employer’s instruction letter dated 06.03.2015.
57