Page 27 - World Of Nurol Magazine 28
P. 27
Amounts realized on the basis of main
construction items for Phase 1 are as
follows:
STRUCTURE TYPE QUANTITY
Main Motorway Length : ~52,5km
Suspension Bridge: 1 NOS /2.907 m
Tunnel : 1NOS/3.522m
Viaduct: 8 NOS/4.922 m
Bridge: 12 NOS/528m
Overpass : 15 NOS/1.397m
Boxculvert: 98 NOS/6.171 m
Underpass: 49 NOS/3.015 m
Intersection : 5 NOS
Motorway Service Area: 3NOS
Motorway Operation - Maintenance Facility: 1 NOS
Tunnel Operation Facility: 1 NOS
As of 30 June 2016, the construction of Phase 1 was completed and opened to traffic.
Phase 2 A (Main body length approx. 25 km, between Gemlik - Çağlayan (Existing Bursa Ring Road) intersections)
Selçukgazi Tunnel is located in Phase 2 A. The construction and acceptance of Phase 2 A has been completed. It has been
opened to operation since 12 March 2017.
Amounts realized on the basis of main construction items for Phase 2 A are as follows:
Completed
Total Nos Total Lenght
Nos
Viaduct 6 4.502 6
Underpass 8 500 8
Overpass 9 199 9
Bridge 5 260 5
Box Culvert 48 4.824 48
Tunnel Construction (Selçukgazi) 1 1.025 1
Intersection 1 1
Service Area 1 -
Phase 2 B (Main body length approx. 306 km, between Existing Bursa Completed Nos
Ring Road Karacabey - İzmir Karasuluk intersections) Belkahve Tunnel is Reinforcement Viaduct 2
located in Phase 2 B.
Underpass 28
The construction and acceptance of 20 km section of Phase 2 B between Overpass -
(Balıkesir-Edremit)-İzmir Kemalpaşa Karasuluk intersections has been Bridge 1
completed. It has been opened to operation since 8 March 2017.
Box Culvert 74
Note: Kemal Paşa State Connection Road junction located within the Tunnel Construction (Belkahve) 1
abovementioned 20 km section was opened to traffic on 20 October 2015. Intersection 2
Amounts realized on the basis of main construction items for the
abovementioned 20 km section are as follows: Service Area -
27