Under two separate contracts which are signed by ADM and      and 57 km drainage piping and 90 km drainage channels are
        our company on 2012, 3  parcel “Sidi Smail – Oualidia” and    carried out.
                              rd
        4 parcel “Oualidia – Safi” sections that totals 82.1 km will
         th
        be constructed.                                               98% of works on underpasses and overpasses are completed
                                                                      and accessory and terminating works are underway.
        Under the coverage of projects, there are 7.1 million m       Currently, together with sub-grade and base course, hot
                                                             3
        excavations, 8.6 million m  made-up ground, 230 thousand      mix asphalt spreading carried on and total 81 thousand km
                                3
        m  concrete, 860 thousand tons hot mix asphalt and            binder, 58 km wearing application are completed.
          3
        various engineering structures.
                                                                      Project is carried on at full steam; hand over is planned on
        Up to date, total 7.1 million m  excavation and 8.5 million m    March 2016.
                                                             3
                                  3
        made-up ground, 8.300 tons ironwork, 182.000 m  concrete