Page 25 - World Of Nurol Magazine-26
P. 25
8 km length PTO Motorway Project will provide connection Substructure works are started at 5 of 22 viaducts be about balanced
to East West Motorway, which is main transportation way, cantilever and precast beam which establish approximately 11
4from Tizi - Ouzou City Bouira Province. km of 45 km route. Besides, basic, elevation manufacturing are
continuing on 3 viaduct. On the other side, excavation works are
With Job Order (ODS) being given on March 2, 2014 by Algeria continuing on the exit portal of Bouira tunnel (935 m) from two
National Motorway Administration (ANA) as ÖZGÜN- NUROL- tunnels on the route.
ENGOA Partnership works are started. Mobilisation activities of
the project are completed and the route earthwork operations are Draa El Mizan entry portal excavation works are completed and
made as contractual at 60%. excavation and fortification works started at right - left tunnels.
Douera Dam near Douera District at 27 km southern west of capital city Alger is the first project
that our company executed in Algeria. In order to irrigate farm lands (17.200 Ha) in Mitidja
Lowland and rise of underground water level with filtration, temporary admission of built
Douera Dam is made on 30.09.2014.
Official launch of the dam is made on 4.07.2015 by Algeria Prime Minister Excellency
Abdülmalek SELLAL and water holding is started on the dam. Work site demobilization is
completed.