Page 32 - World Of Nurol Magazine-24
P. 32
KAZLIÇEŞME
AGENDA STATION
Nurettin DEMİR
Project Manager of NUROL GAMA MARMARAY
Detailed information we obtained from Mr. Nurettin Demir, When did the project begin?
our Marmaray Project Manager, is as follows:
The contract date of our project is 25.05.2004; effective date
Could you please tell us about the formation of Gama of the project is 16.07.2004; and the construction started on
- Nurol Company? 27.08.2004.
The Gama- Nurol Joint Venture, comprising of GAMA Who were the partners and what was Nurol’s share in
Endüstri Tesisleri İmalat ve Montaj A.Ş. and NUROL İnşaat the project?
ve Ticaret A.Ş. was established on 01.10.2003 in order
to perform the “Marmaray Project Contract BC1 Railway Japanese partner of Gama- Nurol in the project is Taisei
Bosphorus Tube Crossing, Tunnels and Stations.” Corporation which has 75% share of the liability. Liability
share of the joint venture is defined as %25 and this share
is equally allocated to the two companies (12.5% each).