Marmaray


                     Uskudar, Yenikapi and Ka-
                            Stations;
                                       structural
                  zlicesme
                  constructions of Ayrilikcesme,
                  Yenikapi and Yedikule Ventilation
                  Buildings; TBM tunnels between
                  Yedikule and Yenikapi, and inter-
                  nal construction works of Yenika-
                  pi NATM turnback tunnel, under-
                  taken by Gama-Nurol partnership,
                  of the Marmaray Project which is
                  one of the biggest ongoing proj-
                  ects of the construction sector
                  in Turkey have mostly been com-
                  pleted. As Gama-Nurol partner-
                  ship, our progress rate is 94,12%
                  and the works progress rate for
                  initiation of finishings and elec-
                  tromechanical works reached 97%
                  completion rate.

                     4-lane viaduct between Usku-
                  dar-Kadikoy which is a part of the                                                Yenikapı Station - Steel Roof
                  ongoing, large-scale highway and
                  intersection  work  carried  out  by
                  our partnership in Ayrilikcesme
                  which is the starting point of the
                  Marmaray Project in Anatolian
                  side will be brought into service
                  through a ceremony with the par-
                  ticipation of Mr. Binali YILDIRIM,
 Marmaray
                  H.E. the Minister of Transport.

                     Monthly meetings have been
                  held with the participation Em-
                  ployer Representative and Mr. Bi-
                  nali YILDIRIM H. E. Minister since
                  August, 2012 for the rail services
                  to come into operation in Sirkeci
                  Station by October, 2013. Con-
                  struction works of the tunnels
                  of Sirkeci Station and of passen-
                  ger  entry  structures  have  been                                             Uskudar Station – Platform Floor
                  progressing in with a higher rate
                  than planned in order to recover
                  for the time lost in archaeological
                  excavations which lasted almost
                  73 months in total.