                                                                                  The  Douera  Dam,  the  first  Project  realized  in
                                                                                  Algeria  by  NUROL,  has  been  totally  completed
                                                                                  and the final acceptance has been conducted on
                                                                                  15.10.2017 after a warranty period of 3 years. The
                                                                                  dam,  located  at  27  km  South-West  of  Algiers,
                                                                                  provides  potable  water  to  the  Capital  city  and
                                                                                  irrigation water to the nearby farmlands of 17.200
                                                                                  ha in the Mitidja plain.






            SOUK






            TLETA







            DAM







             Project Manager: Kamil İlhami GÜMÜŞDAĞ


           The  Souk  Tleta  Dam,  the  second  Project  of
           NUROL in Algeria, shall provide potable water
           to the  Capital  Algiers  from  its  100  million m
                                                      3
           reservoir. It is a zoned earth fill embankment
           dam  with  a  total  volume  of  3.000.000  m
                                                      3
           earth-moving including the side embankment
           (dig de cole).

           After a suspension period of about 4 years owing to the expropriation problems in the lake area, the Project has been resumed
           eventually since July 2016. At present; the diversion tunnels, no 2 of 8 m diameter for a length of 375 m, have been completed
           including concrete lining, construction of the diversion inlet and outlet structures is in progress for realization of the river
           diversion in early 2018. Besides, spillway excavation has been performed by blasting since June 2017. The dig de cole with an
           embankment of 200.000 m  has been completed. The dam embankment and spillway concrete is scheduled to commence
                                     3
           by the middle of 2018.