Suspension bridge construction works are included in the following tables based on main construction quantities.
PROCESS TABLE OF TOWER FUNDATION, ANCHORAGE AND CAISSON PROGRESS TABLE OF STEEL WORKS
General
Total
Planned Total General Work Items Unit Planned Total Realization This Period Realization Progress
Quantity
Work Items Unit Total Realization This Period Realization Progress
Quantity Fabrication
South Anchorage Excavation m³ 89.300 89.300 89.300 100% Steal Shaft TON 2.072 2.072 2.072 100%
Tower Panel NOS 400 400 400 100%
North Anchorange Excavation m³ 37.125 37.125 37.125 100% Deck Panel NOS 3.246 3.246 3.246 100%
South Tower Foundatıon Excavation m³ 50.000 50.000 50.000 100% Main Cable TON 19.300 19.300 19.300 100%
North Tower Foundatıon Excavation m³ 25.547 25.547 25.547 100% Hanger Rope TON 740 740 740 100%
South Tower Foundation Pile NOS 195 195 195 100% Erection
North Tower Foundation Piıle NOS 195 195 195 100% Steel Shaft NOS 4 4 4 100%
Tower Block NOS 100 100 100 100%
South Anchorage Concrete m³ 85.808 85.808 85.808 100% Beck Segment NOS 132 132 132 100%
North Anchorange Concrete m³ 36.016 36.016 36.016 100%
Main Cable NOS 224 224 224 100%
South Tower Foundation m³ 21.295 21.295 21.295 100% Hanger Rope Clamps NOS 202 202 202 100%
North Tower Foundation m³ 21.295 21.295 21.295 100% Hanger Rope NOS 210 210 210 100%
Saddles NOS 12 12 12 100%