BEYHAN 1
DAM
The manufacture and installation works of Beyhan-1 Dam, with its 550 MW installed
NATIONAL han Energy Production and Trade Co. Inc.” (Partnership between Cengiz Construction and
power and the HEPP Hydro-mechanical equipment are performed by “Nurol Machinery and
Industry Co. Inc. / Steel Division” within the scope of the sub-contract signed with “Kale-
Trade Co. Inc. and Özaltın Construction, Trade and Industry Co. Inc.).
Beyhan-1 Dam and the HEPP facilities will be built on Murat River and consist of 4 units
in total. The extent of the work which is undertaken by Nurol Steel (Penstock pipes, tran-
sition, installation bearings, flexible coupling, roller bearing, admission pipe gate, portal
crane, radial gate, drum lifting device, stop log, cone valves and butterfly valves) is 5.000
58 tons in total. 50 % of the manufacture and 10 % of the installation works have been com-
pleted so far. It is planned that the manufacture and installation works are to be completed
until December 12, 2013.