Page 16 - World Of Nurol Magazine-22
P. 16
a company in our qroup
school and of the lodging building in Kumarlı Village, dams are high, regulated stream flow reaches Ceyhan HES
• Construction of a Mosque in Kumarlı Village, and and this enables the firm energy of the plant to be high.
maintenance and reparation of the existing mosques The Ceyhan HES project has benefited national economy
in neighbourhoods, substantially by generating 250 GWh energy annually.
• construction of the 14 km long road linking Karagedik
and Kumarlı Villages to Osmaniye, Could you briefly mention the development stages of
• Maintenance and reparation of the Karatepe Village the project?
Mosque, and the provision of heating, cooling and Important milestones regarding performance of the
ventilation systems, project are as below.
• Maintenance and reparation of Kanlıgeçit and Düziçi
Gendarmerie Stations, • Subsequent to the licensing in June 2007, system
• Environmental planning of Değirmenocağı connection contract has been signed with TEIAŞ.
Gendarmerie Station and the provision of reparation • Meetings related to the financing of the project have
materials, been terminated in November 2007 and loan
• Environmental planning of a primary school in contract has been signed with Akbank-TSKB.
Central Osmaniye and the construction of a basketball • On the subject of provision of Electro mechanic
court, Equipment which will be used in our both plans, a
• Maintenance and reparation of Community Facilities contract has been signed with Alstom in November
of Osmaniye Forestry Department. 2007.
• Urgent nationalization has been realised by issuing
Can you please inform us on the process? the decision of public utilities from Energy Market
Water Use Right Agreement was signed in May 2006 Regulatory Authority and actually, construction of
regarding the performance of CEYHAN HES Project by Oşkan HES plan has commenced in January 2008.
our company with General Directorate of State Hydraulic • In January 2009, montage of Phase 1 electro
Works (DSI). Production License regarding the Ceyhan mechanic works has commenced.
HES project was acquired on 21.12.2006 for 49 years by • In August 2009, montage of Phase 1 electro mechanic
applying to EPDK (Energy Market Regulatory Authority) works has commenced.
following the agreement concluded with DSI. After • In May 2010, tests of the units related to Oşkan
a difficult construction period mentioned above, the Hydroelectricity Plant have been completed and
management period has started. application has been submitted to Ministry of Energy
and Natural Resources for provisional acceptance.
Aslantaş, Berke, Sır and Menzelet Dams are located in • Provisional Acceptance with the Provisional
the upstream of our plant. As the storage volumes of these Acceptance Committee established by Ministry of