Jumeirah Park Infrasructure Project, which comprises all within the scope of configuration contract that is signed with
components of the substructure like road, lightning, middle Nakheel company.
and low voltage electric llines, sewerage system, garden
irrigation, rain and drinking water lines, transformer buildings In addition, to Nurol’s successfully completed projects,
and pump stations that will service to 2760 villa at 400 ha Nurol is focusing on landmark and special Projects in
area, is started with 110 million $ price in 2006, Jumeirah Villas Dubai, like the Route 2020 Dubai Metro, by leading an
project, which comprises 856 villa construction that have
2
200.000 m construction area, started 203 million $ price in international Joint Venture.
2007, Jumeirah Park Package-7 villas project, which comprises
2
453 villa construction that have 160.000 m construction
area, started with 280 million $ in 2008 within the scope
of contracts with employer Nakheel company. Employer
Nakheel company, who is effected from the economic crisis
that is experienced in the world at the last quarter of 2008,
soon after decided not to continue to Jumeirah Park Package-7
villa project and cancelled the contract unilaterally. At the
other two project that continue works are slowed down
and stopped for a while. With reconstruction contract and
additional contracts that are signed later the works started
again, against all the odds Nurol finished the two project on
2012-2013 successfully worthily and they are submitted to
the employer following the maintenance periods. Currently
attempts are continuing and necessary steps are being taken
19