Page 17 - World Of Nurol Magazine-26
P. 17
PROJECT BRIEF The Project consists of Main Tunnel (1198 m), Branch
Tunnels (225.72 m), Under Ground Security Control
nd
Commencement Date : 2 FEBRUARY 2014 Building, Pump Room & MEP Systems.
st
Completion Date : 1 OCTOBER 2016 The tunnel is successfully completed on time and currently
under Operation and Maintenance period..
Type of Contract : Design and Build Lump Sum Contract
MILESTONES
PROJECT ABSTRACT
1. Structural completion of Entrance & Exit Link Tunnels to
The object of this Contract, is provide Design and Build Louvre Abu Dhabi – Security Screening Facility (SSF): 20 th
Security Service Tunnel connecting to Louvre Museum Abu September 2014 – Completed on Time
Dhabi, Guggenheim Museum Abu Dhabi, Zayed National
Museum & District Mall on the Saadiyat Island, Abu Dhabi. 2. Completion of Tunnel to allow full operational access
to the Louvre Abu Dhabi – Security Screening Facility: 20 th
The Client is Tourism Development and Investment April 2015 – Completed on Time
Company (TDIC) where M/s. Turner represents the Client
and Tunnel Design performed by local/Malaysian Design 3. Completion of Tunnel : 20 months from commencement
st
Firm M/s. CHSS under Nurol performance. date – 1 October 2015 – Completed on time.
SADİYAT ISLAND