KİĞI DAM AND HEPP
he Kiğı Dam and HEPP located at Bingöl is being
realized under the investment of DSI. This plant
Twill be installed on Murat River. The fabrication
and installation works of hydromechanical equipment is
being carried out by NUROL STEEL within the scope of
permanent mechanical equipment project.
The fabrication work of penstock pipes of the project is
started in the first half of year 2014 and the fabrication
of them has already been completed. Hydromechanical
equipment works within the scope of the project are
continuing. The plant will be put into operation at the
end of 2015 and its annual production capacity will be 650
GWh. EX-FACTORY FABRICATIONS
The scope of the contract is including
- Radial gates and embedded elements n addition to the fabrication works in connection with NUROL STEEL’s own contracts, it is also performing the
- Gate Lifting Assembly and control assemblies, fabrication and erection works for hydromechanical and electromechanical items being under the contractual scope
- Bottom Outlet valves & Gates and control Iof foreign companies, such as Alstom, Voith and Andritz. “Spiral Case”, “Rotor Spider”, “Pit Liner”, “Generator Stator
mechanisms, Y.KALEKÖY DAM AND HEPP Frame”, “Draft Tube with Cone”, “Upper & Lower Bracket”, etc. are the examples of such works.
- Penstock pipe and steel supports, More specifically;
- Power plant traveling (mobile) crane and portal ukarı Kaleköy Dam and HEPP, located on Murat
(gantry) cranes river at Bingöl, is being realized at the time of ● 3 pcs 5.400 mm diameter Draft Tube and Cone of Yukarı
Kaleköy Dam and HEPP, which are under the contractual
- Switchyard and cable channel steel structures
Ycompletion.The total installed power of the plant scope of Voith Company, are being manufactured in two
will be 625 MW and the annual production amount pieces. The fabrication of 3 units Spiral Case of Yukarı Kaleköy
will be 1.505 GWh. The fabrication and installation of Dam and HEPP are going on, as well. Pit Liner and Spiral Case
Hydromechanical Equipment are performed by NUROL Pressure Test Gates projects are the works contract of which
STEEL and it will be commissioned at the end of 2015. were recently awarded to NUROL STEEL.
●Artvin Dam and HEPP turbine, generator and switchyard
The scope of the contract is including: equipment are the contractual responsibility of Alstom
- Spillway Cofferdam Gates and embedded Company, for 7 units. The Spillway Cofferdam Gates with
elements and lifting beam, 1.500x5.500x1.6000 mm dimensions are being manufactured
- Spillway radial gates embedded elements and by NUROL STEEL. Currently the fabrication of 4 units of Tail
lifting assembly, water Gates are continuing and it is planned to be completed
- Energy inlet grates, service gates, cofferdam within the year of 2014.
gates and embedded elements, ● Yukarı Kaleköy turbine and generator project is under the
- Power Plant Building inlet pipe covers, contractual responsibility of Andritz Hydro Company. The
embedded elements and gate lifting assemblies, fabrication of Stator Frame (being the most critical parts for
- Penstock pipe and accessories Φ6.400, Φ2.200 fixing the generator and rotors) are currently continuing. The
- Butterfly Valve fabrication, which is performed in two pieces and at 11.500 connection with Çetin HEPP project being under the
- Conic Valve and mm diameter, shall be delivered at the end of 2014. Similarly, contractual responsibility of Andritz Company
- Portal (Gantry) Cranes the derivation Entrance and Exit Tunnels Embedded Elements
contract has been recently awarded to NUROL STEEL, in