ASIAN REGION TREATMENT PLANT CONSTRUCTION (1) PROJECT
For the Asian Region Treatment Plant Construction (1) treatment facility, and its scope includes the construction
project, which was tendered by the General Directorate of a Drinking Water Treatment Plant with a capacity of
of Istanbul Water and Sewerage Administration on 360,000 m3/day and 1 Pumping Station. The construction
January 29, 2024, the joint venture in which Nurol İnşaat period for the Construction, Mechanical and Electrical
was involved made the most advantageous offer with an Works of the Treatment Plant is 900 days, and the period
offer of 2,348,000,000 TL. The project will be carried out for Completion of Field Tests and Commissioning and
within İSKİ's Beykoz, Cumhuriyet village drinking water Making it Ready for Operation is 180 days.