DOUERA                                      The Douera Dam, located near Douera district 27 km southern
                                                                     west of Algiers, the capital city, is the first project having been
                                                                     realized in Algeria by NUROL. The Douera Dam shall provide
                                                                     potable water for the Alger city as well as irrigation water to the
                                                                     farm lands (17.200 Ha) in the Mitidja plain.  The Dam was totally
                                                                     completed including the works of the 2 years warranty period
                                                                     that the final acceptance was performed on 5 October 2016.
                                                  DAM                The inauguration of the Dam was performed on 4 July 2015 by

                                                                     his excellency Abdulmalek SELLAL, Prime Minister of Algeria,
                                                                     and the reservoir impounding had been initiated since then.
























             The Souk Tleta Dam, the second project of NUROL in Algeria,
             has a 100 million m  water-retention capacity, which will be
                                 3
             used for potable water supply to Boumerdes and Algiers cities
             of the Country.  The Dam is a zoned earth fill embankment with  SOUK
             a total volume of 3.000.000 m  earth-moving including the side
                                         3
             embankment. The project consists of two 8 m diameter diversion
             tunnels of each 375 m length,  a scheme of injection galleries
             totally 525 m length, 105.000 m³ concrete and 50.000 m drilling
             for the grout curtain.                                       TLETA
             After the project remained suspended for 4 years owing to the
             expropriation problems in the lake area, the works have been
             resumed eventually since July 2016. Until to date, driving of both
             diversion tunnels were performed by rock blasting and the tunnel
             concrete lining has been completed recently where as excavation  DAM
             of the diversion tunnels inlet structure has been completed
             meantime. The fill placement for the side embankment is on the
             completion stage. The works are carried out at an accelerated
             pace for achievement of the river diversion in 2017.
                                                                          Project Manager: Kamil Ilhami GUMUSDAG
             The works for the cofferdam and spillway has been commenced
             after realization of the deviation of the RN25 state road at date
             23 May 2017.