ALGERIA
Regional Manager: Nurettin DEMİR
Mustafa AVUNDUK(PTO Tunnel Chief), Mehmet OĞUZ(PTO Grupman Manager),
Nurettin AKDENİZ(Nurol Construction Inc. General Manager), Taner UZDIL(PTO
Project Manager), Ali AL (PTO Thopographical Chief), Nurettin DEMİR(Nurol
Construction Inc. Algeria Regional Manager), Mehmet ÖZTÜRK(PTO Concrete
Structures Chief)
Construction work of the highway for the Tizi-Ouzou city the structures, one balanced cantilever viaduct is almost
connection to the main East-West Highway with the length completed and works for four more are being carried out.
of 48 km has been given to the partnership of Özgün-Nurol- For the two tunnels with total length of 2x1.57 km,
Engoa (Groupement O.N.E.) with the 538 million Euros valued construction works at six tunnel faces are going on at the
contract signed on 12.02.2014. With the addendum approved same time. Temporary supports and excavation works have
in December 2016, total BOQ has reached over 600 million reached 610 meters.
Euros.
For the general, over 30% of the total work has been
In three main campsites (Boukhalfa, Draa El Mizane and completed so far.
Djebahia) and in the tunnel site, four concrete plants are in
use and the mobile crusher and an asphalt plant are ready TOTAL QUANTITIES OF THE PROJECT
to be used. For the project, a total of 1200 personnel have 24,9 Millions m³ of Excavation
been hired including Turkish and Algerian locals and with 7,5 Millions m³ of Fill
the machinery more than 550 the works are being carried 1,3 Millions m³ of Concrete
out. Besides our own resources, some Turkish and local 130.000 Tons of Reinforcement Steel
subcontractors are being used as well in our project which 800.000 Tons of Ciment
has a huge importance for both our companies and the local 3,5 Millions Tons of Agregates
people. 122.000 Meters of Piles
2.200 Pieces of Precast Concrete Beams
Within the project, over 11 millions m³ of excavation and 1 10.000 Tons of Pre and Post-Tension Cables
million m³ of fill have already been completed. 45.000 Tons of Bitumius
The project contains of 21 viaducts with a total length of 970.000 Tons of Hot Mix Asphalft
2x10.500 meters including the longest one of 1773 m. Among 1,5 Millions Tons of Plant Mix