ALGERIA



















           Regional Manager: Nurettin DEMİR






                                                                              Mustafa AVUNDUK(PTO Tunnel Chief), Mehmet OĞUZ(PTO Grupman Manager),
                                                                              Nurettin AKDENİZ(Nurol Construction Inc. General Manager), Taner UZDIL(PTO
                                                                               Project Manager), Ali AL (PTO Thopographical Chief), Nurettin DEMİR(Nurol
                                                                               Construction Inc. Algeria Regional Manager), Mehmet ÖZTÜRK(PTO Concrete
                                                                                                  Structures Chief)

                  Construction  work  of  the  highway  for  the  Tizi-Ouzou  city  the structures, one balanced cantilever viaduct is almost
                  connection to the main East-West Highway with the length  completed and works for four more are being carried out.
                  of 48 km has been given to the partnership of Özgün-Nurol-  For the  two  tunnels with total  length  of 2x1.57  km,
                  Engoa (Groupement O.N.E.) with the 538 million Euros valued  construction works at six tunnel faces are going on at the
                  contract signed on 12.02.2014. With the addendum approved  same time. Temporary supports and excavation works have
                  in December 2016, total BOQ has reached over 600 million  reached 610 meters.
                  Euros.
                                                                            For the general, over 30% of the total work has been
                  In three main campsites (Boukhalfa, Draa El Mizane and  completed so far.
                  Djebahia) and in the tunnel site, four concrete plants are in
                  use and the mobile crusher and an asphalt plant are ready  TOTAL QUANTITIES OF THE PROJECT
                  to be used. For the project, a total of 1200 personnel have  24,9 Millions m³ of Excavation
                  been hired including Turkish and Algerian locals and with  7,5 Millions m³ of Fill
                  the machinery more than 550 the works are being carried  1,3 Millions m³ of Concrete
                  out. Besides our own resources, some Turkish and local  130.000 Tons of Reinforcement Steel
                  subcontractors are being used as well in our project which  800.000 Tons of Ciment
                  has a huge importance for both our companies and the local  3,5 Millions Tons of Agregates
                  people.                                                   122.000 Meters of Piles
                                                                            2.200 Pieces of Precast Concrete Beams
                  Within the project, over 11 millions m³ of excavation and 1  10.000 Tons of Pre and Post-Tension Cables
                  million m³ of fill have already been completed.           45.000 Tons of Bitumius
                  The project contains of 21 viaducts with a total length of  970.000 Tons of Hot Mix Asphalft
                  2x10.500 meters including the longest one of 1773 m. Among  1,5 Millions Tons of Plant Mix