Besides performing the fabrications regarding • Within the scope of the Upper Kaleköy Turbine &
contracting projects, Nurol Çelik (Nurol Steel ) carries Generator Project which is undertaken by Andritz
out hydromechanical and electromechanical fabrications Hydro Company, the manufacturing of the “Stator
of generator and turbine projects to be undertaken by Frame” having 11.500 mm diameter (54 tons), which
foreign origin companies such as Alstom, Voith and is one of the most critical parts to which generator
Andritz such as “Spiral Case”, “Rotor Spider”, “Pit Liner”, and rotor would be mounted, has been made as two
“Generator Stator Frame”, “Draft Tube With Cone”, parts and delivered. Regarding Çetin HPP project
“Upper & Lower Bracket”. To exemplify; which is undertaken by Andritz Company similarly,
Derivation Entrance and Exit Tunnels Embedded
Some of the projects performed for Alstom, Voith and Elements have been completed and delivered to the
Andritz; Client.
• 3 pc of 5.400 mm Diameter “Draft Tube” (49 tons x
3 Units: 147 ton) for the Upper Kaleköy Dam & HEPP In addition;
project which is undertaken by Voith Company has
been fabricated in eight pieces. Manufacturing of • The 4.718 tons of the total 5.790 ton of the hydro
the “Spiral Case” Pressure test Caps, belonging to mechanical manufacturing,belonging to the Upper
the same project have been completed and delivered Kaleköy Dam & HEPP of which construction is
as well. Also, the manufacturing of the 10.940 meter ongoing by the Kalehan Elektrik Üretim ve Ticaret
diameter “Spiral Case” 3 Units (107 tons x 3 Units: 321 A.Ş. (Kalehan Power Production and Trade Corp.) has
ton) and “Pit Liner” (10 ton x 3 Units: 30 ton), which been manufactured in our factory and then delivered.
are appurtenant to the Upper Kaleköy Dam Project The manufacturing of 1.072 tons is ongoing in our
have been completed, final acceptance tests of factory.
productions were made by the client and delivered.
• The hydro mechanical manufacturing of the 4.266
• The Artvin Dam and HEPP which is undertaken by tons of the total 4.381 tons of the Kiğı Dam and HEPP,
Alstom Company within the scope of the Project of of which construction is ongoing by the Özaltın İnşaat
the equipment the Turbine, generator and switchyard (Özaltın Construction) has been manufactured in our
equipment, the manufacturing of Spillway Stop Logs factory and then delivered. The manufacturing of 115
(30 tons x 7 units: 210 ton) and 4 Unit tail water Caps tons is ongoing in our factory.
(102 tons) have been completed and delivered.