Page 38 - World Of Nurol Magazine-26
P. 38
completed of the last module, and by pushing
forward 1.123 meters long one piece to 40 meter
ahead.
And in 5th of July, you realized
another Turkey record as well.
What do you say about this issue?
As a matter of in fact, when we mount the first
span with 2 thousand 350 ton heavy lifting
operation, we had been broken Turkey record
as quietly. The second span was completed in
5th of July, and by this operation we have broken
heavy lifting record that belongs to us and lifted
128 meter long, 36 meter wide 2 thousand 600
tone part to 57 meter high.
Here engineering science becomes a part of
this activity. If you want to push a 22 thousand
500 tons of material, you have to minimize the
friction of this material. If you able to reduce
friction to 5 percent, with the best technology
used in the World (The state of art technology)
you must realize a pushing with 1300 ton force.
Or, in order to lift a 2 thousand 600 ton weight
from 8 points, you need a lifting equipment with
a capacity of at least 325 tones.
I’m trying to say, as long as figures grow and
the issue they lose their quantities they have,
in proportion as they grow and the matter
becomes a requirement has to be overcome.
With an investment of approximately $ 11
million a construction yard was established At this point we transfer the work to philosophy.
at the southern end of the viaduct. Success had four steps. Dreaming, believing,
working hard and share. The item I have to explain
For the box section the Sefine shipyard and for mostly was to share. No success is possible
the panel manufacturing Eran Mühendislik have without sharing. We overcome every difficulty
been selected and production processes was we’ve encountered by believing these items from
started. The process, production and quality the moment we started the construction of the
control structures were constituted in order project.
to fabricate over 2 thousand ton per month.
Nevertheless, the narrowest point of the And the most important thing to emphasize is
hourglass was the point being capable of making having a team that dedicated their two years
a production continuously with a capacity to this project, with dedication and exemplary
obtained by our construction yard to which 40 diligence forming the hidden subject of the
years of steel production factories cannot reach. above sentence and the belief of this team for
Another point, being more critical was in need completion of this project.
of low tolerances and very high
quality requirements, at such
36 meter wide a giant structure
where steel usage is fit - up
with the orthotropic sectional “And the most important
solutions. In this field, by thing to emphasize
means of two gantry cranes
with a total capacity of 200 is having a team that
tons, we have completed 22
thousand 500 tons erection dedicated their two years to
work in 15 months. Of course, this project, with dedication
with the help of project -
specific designed hydraulic and exemplary diligence
and mechanical equipment. forming the hidden subject
In April, we have been realized of the above sentence and
the installation of world’s the belief of this team for
heaviest deck by means of the
drive with the incrementally In general framework, has being
completion of this project.”
lauching method with the within a powerful and reliable
38