xcavation studies of Öceli tunnel (2.010 meters
x 2) within the scope of Ordu Beltway project
Eof which the construction is undertaken by our
company have been completed with the combination
of two tubes on 14 March 2014. Excavation and final
concrete coating works are going on in Boztepe (3.300
meters x 2 ) ve Terzili (1.180 meters x 2 ) tunnels.
Ordu Beltway of which the construction is under
taken by Nurol - Yüksel - Özka - YDA Partnership
shall be constructed as a complementary part of
Black Sea Coastal Road in conformity with the
purposes of meeting the standards required for
transit traffic and reducing the urban traffic.
Ordu Beltway Project which is revised by changing
the route, separates from Akçaova River and passes
under Boztepe by a tunnel and passes Civil Creek,
Melet River and Turnasuyu by a viaduct and then
JOLLY connects to the coastal road ahead of Turnasuyu
River. With the change in the route, the total length
of the project has reached from 19,1 to 21,4 km.
On the Ordu Beltway which will be constructed as 2x2
ROAD m divided road with 26 m platform width, 4 viaducts
which are 2.478 in length in total, 6 (double tube)
tunnels which are 18.529 m in length, 6 junctions in
total of which 3 is interchange, bridge which is 30
m in length, 9 underpass bridges which are 287 m
in length and 46 box culverts which are 2.160 m in
length.
of COAST Until today, 60 % of the project has been completed
on the basis of contract estimate, of which the
construction has started in 20.03.2012.